Construction of Heshmat River Retaining Wall in Astaneh-ye Ashrafiyeh

Client: Astaneh-ye Ashrafiyeh Municipality

Designer and Project Supervision: Civil Engineering Deputy of Astaneh Municipality

Contract number: 6-99-14-13752

Start date: 2021.01.06

End date: 2022.01.05

Location: Gilan Province, Astaneh-ye Ashrafiyeh County

Project Specifications and Overall Objective:

The construction of a stone retaining wall along the 100-meter-long and 6-meter-high edge of the Astaneh water channel. The project involves the following operations:

  • Earthwork operations, including excavation and backfilling, with a volume of 17,000 cubic meters.
  • Concrete pouring operations with a volume of 650 cubic meters.
  • Stonework operations using rubble and malon stones, with a volume of 2,200 cubic meters.