Construction of Gerdakal-Ferdowsi River Protective Wall (Western Side) – Nowshahr

Client: Nowshahr Municipality

Designer and Project Supervision: Civil Engineering Unit of Nowshahr Municipality

Contract number: S-98-3775

Start date: 2019.07.06

End date: 2020.01.05

Location: Mazandaran Province, Nowshahr County

Project Specifications and Overall Objective:

The construction of a stone protective wall on the western side of the Gerdakal-Ferdowsi River, with a length of 286 meters and a wall height of 8 meters, was undertaken for the purpose of developing an urban riverside path, stabilizing the soil, and protecting the residential houses along the riverbank. The project’s operational volume includes the following activities:

  • Stonework operations using rubble and malonne stones, with a volume of 12,000 cubic meters.
  • Concrete pouring operations, with a volume of 3,800 cubic meters of concrete.
  • The amount of rebar used in the project is 65,000 kilograms.
  • Earthwork operations, including excavation and backfilling, with a volume of 115,000 cubic meters.
Preparation and implementation of asphalt paving for the streets of the lower neighborhood of Handeh Khaleh village