Pipe laying operations project to collect and direct surface water in Kamalshahr, Karaj
Project Overview
Project Title: Surface Water Collection and Drainage Pipeline Construction – Kamalshahr City
Client: Kamalshahr Municipality
Design and Supervision Consultant: Municipality Civil Engineering Department Mr. Mehdi Sarai
Contract Number: 2660/140
Start Date: 17 ⁄ 4 ⁄ 2025
Completion Date: 17 ⁄ 4 ⁄ 2026
Project Location: Alborz Province – Kamalshahr – Shahid Beheshti Street and Bagh Zamani Street
Project Title: Surface Water Collection and Drainage Pipeline Construction – Kamalshahr City
Client: Kamalshahr Municipality
Design and Supervision Consultant: Municipality Civil Engineering Department Mr. Mehdi Sarai
Contract Number: 2660/140
Start Date: 17 ⁄ 4 ⁄ 2025
Completion Date: 17 ⁄ 4 ⁄ 2026
Project Location: Alborz Province – Kamalshahr – Shahid Beheshti Street and Bagh Zamani Street
مشـخـصـات و هـدف کلی پـروژه :
- طول مسیر لولهگذاری: 2,550 متر
- نوع لوله: لوله بتنی مسلح
- قطر لولهها: 120 و 140 سانتیمتر
- محل اجرا: خیابان شهید بهشتی و خیابان باغزمانی
- هدف اجرایی: احداث کلکتور اصلی برای جمعآوری و هدایت آبهای سطحی شهری
این پروژه با هدف کنترل و مدیریت روانآبهای سطحی و جلوگیری از آبگرفتگی در معابر شهری در کمالشهر اجرا میگردد. عملیات اجرایی شامل احداث کلکتور اصلی به طول بیش از 2.5 کیلومتر با لولههای بتنی تقویتشده، در خیابانهای شهید بهشتی و باغزمانی میباشد که باعث جمعآوری، انتقال و هدایت اصولی آبهای سطحی به مسیرهای خروجی تعیینشده خواهد شد.